Worked Field Engineering Example20-Ton Hydraulic Excavator (1.00 m³ SAE Heaped Bucket) Digging Bank Clay & Gravel Into a 25-Tonne Dump Truck
Step-by-step verification of loose vs. bank volume per pass, suspended bucket payload, 50-min/hr hourly BCM production, and haul truck pass-matching.
1. Loose & Bank Volume per Bucket Pass: A 20-ton excavator with a rated V_heaped = 1.00 m³ (1.31 yd³) bucket excavates bank clay/gravel mix (FF = 95%, Swell = 25%, ρ_loose = 1,600 kg/m³, ρ_bank = 2,000 kg/m³). Loose volume per pass is V_loose = 1.00 × 0.95 = 0.95 LCM (1.24 LCY). With load factor LF = 1 / 1.25 = 0.80, bank volume per pass is V_bank = 0.95 × 0.80 = 0.76 BCM (0.99 BCY).
2. Pass Payload & Tipping-Load Check: Material mass per pass is M_pass = 0.95 m³ × 1,600 kg/m³ = 1,520 kg = 1.52 tonnes (1.68 US short tons), utilizing 60.8% of the 20-ton excavator’s 2.50 t safe rated payload allowance (SAFE).
3. Cycle Time & Hourly BCM / LCM Production: At a 90° swing angle, total cycle time is T_cycle = 6.0 s (load) + 4.5 s (swing loaded) + 2.5 s (dump) + 4.0 s (swing empty) = 17.0 s. At 83.33% (50 min/hr) job efficiency, the machine completes N_hr = (3600 / 17.0) × 0.8333 = 176.46 cycles/hr, producing 134.1 BCM/hr (175.4 BCY/hr), 167.6 LCM/hr (219.3 LCY/hr), and 268.2 tonnes/hr.
4. Haul Truck Pass-Match Audit: Loading a 25.0 t highway dump truck requires 25.0 / 1.52 = 16.45 → 16 passes (4.53 min spot time), flagging UNDERSIZED_EXCAVATOR_TOO_MANY_PASSES. Pairing that 25 t truck with a 45-ton excavator (2.40 m³ bucket, 3.46 t/pass) reduces loading to 7 passes, or pairing a 20-ton excavator with a 9–10 t site dump truck achieves 6 passes.